How To Model The Throughput Gain Before You Buy Another Instrument

Share
Advertisement

Anyone who has taken on laboratory management finds themselves in an all-too-familiar discussion at some point. The washer is the bottleneck, the plates are backing up against it, and another unit will clearly help. Then finance asks the one question that few would willingly answer: exactly how many more plates per day do you think?

How can you quantify improvement without a convincing number? A vendor spec sheet defines one instrument, not your process, and a spreadsheet full of assumptions won’t survive the first inevitable question.

Selling any kind of automation solution always comes down to this moment, and making the most of it is the point of good laboratory automation solutions. Process estimation in Genera, Retisoft Inc.’s laboratory workflow scheduling software, lets you use your own information to model a run and develop a realistic idea of the benefits. This guide discusses the estimation feature, where the data comes from, and how it was applied in one ELISA workcell automation case to quantify the value of a second washer.

Advertisement

People Also Ask

What is process estimation in lab automation?

Process estimation estimates the time a scheduled run will take based on the expected runtime of each step. Genera iterates through the entire batch count in seconds to estimate the total run time.

How is estimation different from simulation?

Simulation gives a visual representation of plate movement throughout the process to help validate process logic. Estimation uses expected runtimes for each step to predict the total run time without animating plate movement.

Do I need the new instrument to model its impact?

No. You can add the anticipated instrument to the model with expected runtimes and compare the estimated run time to your current configuration.

Why Automation Business Cases Stall

Capital committees purchase quantities, not intuition. The problem is that a new instrument’s value only becomes apparent after purchase. Before that point, an in-house laboratory has only three weak indicators: vendor cycle times, simplistic spreadsheet analysis, and the experience of the person making the request.

None of these account for how laboratory automation systems make decisions. A manually measured washing cycle fails to consider that the robot has other instruments to serve, the incubation holds plates in place, and a second process must share the same reader. Reviewers recognize this and discount the request.

Simulation Against Estimation

Genera offers two ways to run a process without committing samples. They answer different questions, and mixing them up leads to misleading numbers.

What Simulation Shows You

Simulation runs the process with instruments in simulation mode while plates move across the on-screen workspace. Use it to confirm process logic: lanes link correctly, look-aheads hold the right nests, decision nodes branch as planned. Both tools live inside the same lab automation software you use to run the deck, so you don’t need a separate modeling package.

Since simulation isn’t predictive of actual runtime, you’ll see a simulated five-plate run complete in 27 seconds, since every step in a simulated work cell completes instantly. For a full overview of how Genera schedules, simulates, and runs lab workflows, see our complete guide to laboratory automation solutions with Genera.

What Estimation Shows You

Estimation is animation-free; Genera will iterate through the entire batch quantity, apply an estimated duration to each activity, and provide an overall run time, along with a batch chart showing each plate’s progression.

The same five-plate dispensing process, with estimated realistic step durations, yielded an estimate of 3 minutes 48 seconds; use that number for the budget meeting.

Where The Timings Come From

An estimate is only as good as its inputs. Genera gives you two sources, plus a choice in how to summarize them.

Setting Durations Manually At Task Level

Each activity node has a Scheduling tab with an Estimated Duration field. Say a robot move from a hotel to a reader takes about 30 seconds. Enter 30 seconds. This is useful for initial planning or instruments not currently on the deck.

Capturing Durations From A Live Run

The better option is to use your own data. After a live run completes, go to the post-run operations in the task view and export the estimated durations. Genera will make a copy of the process with every duration filled out from the run.

Mean Or Maximum Across Batches

The export asks how to summarize timings across batches: the mean or the maximum. In the ELISA webinar, Retisoft’s applications engineer noted run-to-run variation is typically a matter of seconds.

Our recommendation: use the mean for day-to-day planning and the maximum for anything going in front of a capital committee. A conservative estimate the lab later beats builds more credibility than an optimistic one it misses.

Modeling A Bottleneck Before You Spend

Before asking what a new instrument adds, confirm where plates wait today. A simple field test: watch the robot arm. In laboratory robotics and automation, the arm touches nearly every plate, so its idle time shows where the process waits. If the arm is idle, refer to Genera to determine which step is active. Often, idle time is caused by lengthy incubation or a slow liquid-handling step, such as a serial dilution

The batch chart for a live run or an estimate will reflect this activity onscreen, with plates piling up behind the slow step.

Once you’ve identified the bottleneck, model the change. In Genera, instruments of the same type occupy a common zone, and the process routes plates to the first available unit. Adding a second washer to the washer zone is a configuration change, not a process change.

A Worked Example From A Live ELISA System

This example comes from a live Retisoft webinar on ELISA automation. The workcell, designed and built by Retisoft partner Lab Integrators, a division of Copia Scientific, contained nine instruments including a liquid handler, sealer, peeler, incubator, washers, a bulk dispenser and a reader.

The Baseline Run

The live demo processed two ELISA plates through three assay steps: adding samples and standards, washing the plate, and stopping the reaction before reading. At the end of the run, the applications engineer exported the actual values from the finished task.

He was then asked to predict the time for a heavier workload of processing ten ELISA plates with ten wash cycles each using only one washer. He calculated it would take 2 hours 32 minutes.

The Same Run With One More Washer

A second washer already sat on the deck but was disabled in the software. He enabled the instrument, kept every other setting the same, and ran the estimate again. The result: 1 hour 41 minutes.

Because the washer was already part of the system, the comparison needed no extra hardware or device connection.

What The Difference Represents

The second washer cut the estimated run by 51 minutes, roughly a third of the total. Keep the context in mind. The demonstration covered only three stages of the assay and used shortened incubation times. A full-length ELISA at production volume behaves differently, and the only reliable way to size the gain is to run the same exercise on your own process.

The value of the method is the comparison itself: same process, same plates, same durations, one variable changed.

Testing Instruments You Do Not Own Yet

The second washer in the ELISA example was already purchased. Most labs have an instrument on a quote. Retisoft’s applications engineer demonstrated exactly that in the webinar, filling in estimated durations, then showing how another washer, peeler, sealer, or liquid handler will impact the process without having the instrument on hand.

In reality, take durations for the existing steps from a running export and enter the durations for the new instrument manually using the vendor’s cycle times or a demo run. Then place the new unit in the same zone as its counterpart and let Genera share the work between the two.

Scaling The Model To Real Daily Volume

Two plate test runs prove the calculation. A business case requires your actual volume. Increase the batch count to a typical day’s work and set parameter variables, such as wash cycles, to values your assay actually uses.

One detail shown in the webinar was estimating workspace. Ten ELISA batches required ten ELISA plates, ten sample plates, and five tip boxes in the virtual workspace before the estimate could run properly.

Because Genera is a vendor-independent laboratory automation platform, the instrument you model does not have to come from the same vendor as your current equipment.

Building The Number Into A Capital Request

Reviewers see many proposals for automated laboratory solutions. A proposal backed by data from the lab’s own system stands apart. A strong request presents two estimates side by side: the current configuration and the proposed one, run at realistic daily volume. Translate the difference into terms reviewers recognize, such as plates per shift, assay turnaround, or scientist hours no longer spent waiting on a run.

State where the durations came from. Timings exported from a live run on your own system, summarized by maximum across batches, carry far more weight than a vendor brochure.

What Estimation Leaves Out

Estimation models the process as written. It does not predict instrument errors, an operator stepping away during a pause, consumable restocking, or reagent preparation outside the system. If a step varies widely from run to run, the estimate inherits the uncertainty.

Treat the result as a well-grounded model, not a guarantee, and revisit it once the new instrument is running live.

How To Run Your First Estimation

  1. Run your process live with a representative batch.
  2. In the task view, export the estimated durations and choose mean or maximum.
  3. Open the exported process and schedule it with the estimate option checked and your daily batch count.
  4. Record the total estimated run time from the task details.
  5. Enable or add the instrument you want to evaluate, keep every other setting identical, and estimate again.
  6. Compare the two results and note the source of every duration.

Prove the Throughput Gain Before the Purchase Order

A second instrument is a capital decision, and capital decisions deserve evidence. Genera estimation turns timings from your own live runs into a side-by-side comparison, so the conversation with finance starts from a measured number instead of a hunch.

Retisoft Inc. helps drug discovery and screening labs build these models around the instruments they already own. If a bottleneck is holding back your throughput, book a Genera demo and bring the process with you.

Frequently Asked Questions

How accurate is genera estimation?

Accuracy depends on the durations it uses. Timings exported from a live run on your own system will give the greatest accuracy. Manual entries are best kept for early planning.

Does estimation move plates or use samples?

No. Estimation is performed purely in software based upon stored durations. Nothing is moved on the deck, and no samples or reagents are used.

Should I use mean or maximum durations?

Use the mean for everyday planning. Use the maximum for capital requests since a conservative estimate that your lab can beat later builds more credibility.

How do I model a second instrument of the same type?

Add the new instrument to the same zone as the existing unit and enter its durations. Genera will send each plate to the first available instrument in the zone.

How long does an estimate take to run?

Far less time than the run itself. Genera avoids animation and computes the total batch count from stored durations, letting you compare scenarios quickly.

Share
Advertisement
Lucy Kentor
Lucy KentorGuest Contributor

Lucy Kentor is a passionate blogger and content writer who enjoys exploring diverse topics and sharing valuable insights with readers. She focuses on creating informative, engaging, and easy-to-understand content that helps readers discover new ideas, gain knowledge, and find practical solutions. Her goal is to make every article useful, interesting, and insightful.